| E.
Trasolini Pool Construction Ltd.
New Construction Renovations & Repairs Pools, Spa's and Fountains |
![]() |
1351
Adanac Street, Van. B.C. V5L 2C4
Ph. (604) 255-8551 Fax (604) 255-6681 Email trasolini@intergate.bc.ca |
Congratulations!!
You have chosen E. Trasolini Pool Construction Ltd. to build your "quality" pool.
The following is an outline of what you may expect during the construction of your pool, and may answer any questions you have.
Pool Construction Outline
Workable working
days:
A standard/normal swimming pool requires
approximately 60 workable days after the
completion of excavation. You will notice as the
pool is being built that work progresses in
stages. It is excavated, formed, steeled, plumbed
and gunited as one overall phase. On some
occasions this work stretches out because of
delays of inspections. poor weather, crew
scheduling, etc. Work cannot be done on days when
weather is unfavourable. Work such as pouring
concrete, setting tile, plastering all can be
ruined from a regular afternoon rain shower.
***Please note that our site crews have no
idea of work schedules. Should you have any
question on scheduling. please contact the office.
It is amazing what goes on behind the scenes in
the construction of your pool. Many people are
directly or indirectly involved in a minimum of 10
skilled phases, from excavation through startup.
Plans and Permits:
The site plan of your pool and yard has been
drawn by our draftsman and forwarded along with
engineered structural drawings to the Building
Department of your municipality for plan check and
permits. The time required for issuance of these
permits varies depending on number of applications
already in the Building Department for processing.
Generally 2-4 weeks.
Contract
Addendums:
Any changes you make from the original
contract, estimate and specifications must be made
through our office. These changes are called
addendums and actually amend your original pool
contract. Should you wish to make changes or want
additional work done, you will have to approve and
sign a work order at an agreed change to contract
price. We certainly understand that changes are
normal and have to be made at times, but changes
that create excess cost due to delivering an item,
pick-up, re-delivery or redoing work already done
naturally results in additional expense and adds
to the total cost of your pool project, plus
delaying the progress of the job.
Excavation:
The pool site should be cleared of trees,
shrubs, existing deck work and other above ground
obstructions. Any trees, shrubs or other plantings
to be saved should be removed, cared for and
replanted by the customer. Excavation and fill
removal is the messiest stage of construction and
quite often creates panic for the inexperienced
customer. The cure is "patience", the
site cleans up shortly after the excavation
process. It should be understood that if you are
on excavation allowance specified in your contract
and additional excavavtion is required, either
from your request or from unusual ground
conditions, the costs could dramatically increase.
Day by day progress reports can be provided upon
your request. Normal excavation and fill removal
time for the average pool is approximately 1-2
days. Any additional excavation and fill removal
cost will be billed accordingly as per contract.
Should the customer desire the remainder of
some fill from the excavation, we would be pleased
to do so, however please be sure of the exact
amount you want as we will not be responsible for
removing it at a later date or supplying extra
fill. The reason for this is the high cost of
handling the material.
Layout:
Our excavating crew will form and layout the
pool as per sketch either provided by the customer
or drawn up by us and approved by the customer
prior to starting. If any changes are desired you
must advise the office immediately.
The following are some points for
understanding during the layout stage.
Plumbing
Placement:
This next phase you will see our plumbers
install the pool plumbing system. The plumbing is
installed as per the contract and engineered
drawings. A highway of Sch.40 PVC piping is
installed to your equipment area and stubbed out
so that the equipment slab can be poured. If the
infloor cleaning system is included in your
contract you will notice a number of pipes
protruding from the bottom of the pool.
Steel Placement:
Steel is installed as per the engineered
structural drawings. Extra steel is used at
various points of high stress which is a highlight
of your E. Trasolini Pool.
The steel process takes from 1 to 2 days depending
on the size and complexity of your pool.
Inspections:
Inspectors will be out after plumbing, layout
and steel work has been completed to check that
our work conforms to municipal and building codes.
You will notice an inspection card posted in a
conspicuous place on your property, generally
somewhere near the pool equipment, on the fence or
the side of the house. Under no
circumstances should this card be
removed.
Gunite:
When the inspectors have given final
approval, the gunite is then scheduled. The gunite
crew will arrive and set up their machine. They
will take precautions to protect the area
surrounding the pool so that your shrubs, trees
and appurtuances will receive maximum protection.
The crew then starts the gunite machine and begins
to gun the concrete into the pool. Please keep
your windows and doors closed while the machine is
in operation due to the dust that is created.
Please keep children and pets away from the
equipment to avoid injury. If there are day
sleepers in the home or people that are irritated
bu excessive noise, this might be a good day to be
away from the home as the gunite machine makes a
considerable amount of noise and there is no way
to avoid it.
Upon completion of the gunite process the
pool will be left to cure for a minimum of one (1)
week. In very hot/dry conditions, the customer
should lightly sprinkle the curing concrete. Do
not worry about the pool filling with water as the
pool is open to ground and will vary with the
water table and rains. Water is removed by our
crew preparing for the next stage.
Progress
Payment:
At this stage, the First payment is due. An
invoice will be delivered by accounts receivable.
Payments play an important part in the scheduling
process of your pool. It is imperative therefore,
that we adhere to a firm policy of being paid for
the work as outlined in your contract. You prompt
payments will enable us to expedite the
construction of your pool.
Coping:
A wood form is installed for an edge that
hangs approximately 1.5" over the pool to
eliminate "splash back" or pool water
from splashing out of the pool. This form
must remain undisturbed as the
slightest change will result in inaccurate coping
level. Please do not allow anyone to walk on
forming. Concrete is poured into the form, then
the deck is poured and then the form is removed.
This usually takes two (2) days.
Electrical:
At this stage conduits are placed for wiring
to underwater light and filter equipment, all
switch boxes are set and all metal objects within
5' of the pool are electrically bonded for safety.
Electrical inspection is made at this time. Please
do not switch the pool light on before pool is
filled. The pool light is constructed to operate
submersed in water only. If itturned on while the
pool is empty, the resulting heat will burn out
the light within minutes.
Decking:
Perimeter of pool is backfilled with granular
fill, formed for deck, rebarred and deck concrete
poured depending on deck finishes desired. This
process usually takes three (3) days.
Tile:
A full selection of tiles is provided to the
customer for selection at this time. After
selection is made our tile setters install the
tile, usually an approximate 8" band around
the waterline of the pool. This installation
usually takes two (2) days.
Progress
Payment:
At this stage the second progress payment is
due.
Gas Line:
Line is run from meter to equipment area,
this is left under pressure for checking by the
gas inspector. If the gas line must be placed
underneath the decking, the gas line inspection
must be made prior to the deck being poured.
Landscaping and
Fencing:
Landscaping and fencing may not be in our
original contract, however, whoever does your work
should understand that fences are required to be a
minimum of 42" high with self closing gates
and latches out of reach of children as required
by law in most areas. Fencing and Landscaping must
be in place prior to plastering
the pool.
Area drainage should be installed keeping in
mind that a minimum ground slope of 1/2" per
foot is required for 25' or to a positive water
course. Uphill slopes should be drained with rock
filled trenches covering perforated pipe. The next
stage is plastering but before plastering it is
important that all projects which create dust,
dirt, muss or smoke (such as raking, burning,
gardening, etc.) be completed. Through it all,
protect the coping and decking as it stains
easily, and also keep debris out of the pool.
Plaster:
The sparkling clarity of a fine quality pool
depends heavily upon keeping the plaster clean
through the crucial curing period. Prevent
sweeping, burning or yardwork in the area until
your pool is full of water. This usually takes
between 1-3 days. Dirt and dust cause stains on
plaster for which E. Trasolini Pool Contraction
Ltd. cannot be responsible. On
plaster day, when the plaster is completed and if
the day is warm the crew will set the hose and
turn on water prior to leaving that day. If the
day is cool, they will set the hose and instruct
you when to turn it on. Once the filling has
begun, never turn off the water
until it has risen to the middle
of the tile row. This is to prevent forming of a
ring (like bathtub ring) which would be extremely
difficult to remove.
Start-Up:
When the pool is full of water our service
man will start-up the pool. The service man will
put the filter into operation and initially treat
your pool water with chemicals. NOTE:
If the electrical work is not part of our contract
please be sure that final electrical hookup is
complete so that we may operate the filtering
system. Uncirculated pool water for extended
periods of time may cause plaster staining. The
pool must be brushed once a day for a period of
one month. Personal instructions
will be provided to you on your pool, pool
equipment, pool maintenance and water chemistry.
Pool Maintenance Contract can be arranged if so
desired.
Cleanup:
Our cleanup crew will remove all our
construction debris and leave your yard and access
area as clean as it was before we started. We do
not do finish grading, planting or seeding, etc.
If any fencing was removed to effect access, it
will be replaced by us only if included in
contract.
We would like to take this opportunity to thank you agian for selecting E. Trasolini Pool Construction Ltd. to construct your swimming pool. Should you desire any additional information, please call, we are at your service.
Respectfully,
Ed Trasolini
President
E-Mail
us
Home /
Thumbnails /
Manual /
Outline /
Plans /
Volume /
Systems